Following on from my previous thread about a concrete workshop floor I'm closet to pouring, I'm after some clear advice on (a) choosing and (b) laying steel mesh in the concrete.
If you are looking for more details, kindly visit Heyou.
After some browsing, I'm getting all materials from Bradfords, https://www.bradfords.co.uk/building-materials/builders-metalwork/steel-reinforcement
1. I know others recommended A142 in the previous thread, but given the increased choice of meshes, I wanted to double check this is still most suitable for a 3 x 5 metres by 5 inch deep workshop floor.
2. I'll need approx 1.5 meshes to cover this floor area. This leads me to ask if there's a technique for how/where to cut mesh (I have a cutting disc fitted angle grinder for that)?
3. How should the two mesh piece be joined, if at all?
4. Does the mesh touch the shuttering, or is there a specified offset in from the shuttering?
And advice gratefully received.
Edited By choochoo_baloo on 07/08/ 14:05:33
Edited By choochoo_baloo on 07/08/ 14:05:52
I cannot claim to be a structural engineer, but this is what I did when re-building a Victorian outhouse whose foundations had failed.
I used two sheets of the 6mm bar stuff (SRF001). these I trimmed to length with an angle grinder & cutting disc. I put them into the concrete after pouring and knowing the concrete would be in bending with tension on the top face, so I pressed the steel in less than 1/3 the concrete depth. Did not tie the steel together, but overlapped it by 4 holes in the mesh – about 2 ft. Edge distance, knowing the edges were likely to be wet, was 3". Less than that could lead to enough oxygen to be present for corrosion.
All in all the slab ended up thicker than expected because the truck had 2.5m^3 when we'd ordered 1.5, and was about 14" thick, so could have done without any steel. However, the old building had lasted 120 years on a 2" thick lime mortar foundation, so how long will this version last with a 14" steel re-inforced foundation? At least as long I hope.
Regards,
Richard.
Sorry, but Ignore Richard and Tracy advice – That is wrong. The steel needs to be in tension and at the bottom of the slab ie: put some spacers (broken thin paving slab) on top of the DPM (Overlaped at the joint) . Put your mesh on top of the spacers (Overlap the mesh at the joints) and wire together if you want with bare iron wire (Not essential but keeps things tidy). Pour your cement and tamp down well. Now make sure the cement sets slowly. If you want a smooth surface, polish it with a float once the initial set starts – you will have to walk on the wet cement to do it, so it needs to be hard enough to do that. Professionals use a power float, but you won't need that.
Contact us to discuss your requirements of Concrete Reinforcing Steel Mesh. Our experienced sales team can help you identify the options that best suit your needs.
You may have to cover the cement to stop it drying out too fast and cracking – even flooding it with water if its hot. Cement will cure under water, so don't be afraid to use plenty.
Apologies to Richard
BobH
Over half a century ago I spent a lot of time digging out and concreting a barn floor and a large area of yard, working alongside a farm worker who never broke into a sweat but had a phenomenal workrate I couldn't hope to match. For the 45ft x 20ft barn floor we hand-mixed with shovels; this is probably why I now suffer chronic lower back pain
We didn't use reinforcing mesh anywhere but we did prepare a good solid hardcore sub-base. None of this area has any signs of serious cracking despite heavy traffic, including tractors and lorries. The base preparation is the critical thing . . . my father was a civil engineer.
Mike.
P.S. I seem to remember buying cement at 3/6 ( 17.5p ) for a hundredweight bag and a 15 ton load of ballast for £1 per ton
Edited By Farmboy on 14/08/ 09:27:28
Posted by Speedy Builder5 on 14/08/ 07:43:09:
Sorry, but Ignore Richard and Tracy advice – That is wrong. The steel needs to be in tension and at the bottom of the slab ie: put some spacers (broken thin paving slab) on top of the DPM (Overlaped at the joint) . ….
Apologies to Richard
BobH
BobH, in my situation it was not wrong. I made a hole in the ground the full size of the building footprint and the slab went under the walls, Being supported in the middle of the floor with minimum weight there and maximum weight at the edges will make my slab hog should there ever be sinkage due to the extra pressure from the walls, so the centre of the slab will be in tension. I did know what I was doing, I simply had not fully explained the situation because it was not relevant to the point I was making. I did not advocate putting the mesh near the top of the slab, just said that was what I did.
When it came to the DPC, I lined the hole with it, then tucked it under the first layer of bricks when building the wall. Also put a further DPC 3 bricks up the outer skin of wall. When it comes down to it, in my case having a building with any form of slab will be better than what was there – and that lasted at least 100 years. In fact a number of the bricks that we re-used had paint inside the wall we dismantled, indicating those bricks are now in their third building at the very least.
Regards,
Richard.
Turn it over the top of the sleeper and tack it down. If you are not building the walls off the sleeper then trim it off once concrete set. If you are building off the sleeper then leave in place and put DPC on top.
If you try to cut it flush before concreting it will more than likely move down with weight of concrete.
Where do the walls actually come as may affect where you turn it up.
Edited By JasonB on 16/08/ 07:01:12
If you want to learn more, please visit our website A252 Steel Wire Mesh.
Sorry for so many concrete questions but I keep discovering new things as time passes. This commercial building I'm looking at possibly buying (or really part of the building...flexspace arrangement). Building is aprox 14,000 sq ft, I'm thinking of buying 6,250 sq ft on right side. The 5,000 sq ft on left side (middle spaces already sold) offers a unique opportunity to see how they did the slab as they didn't complete the slab. The slab is basically a rectangle around the perimeter of the inside aprox 15 feet with the middle area left open. This, apparently so that new owners could run pumbing to suit their needs.
Anyhoo, from this unfinished slab I can see it only 4 inches thick. Plastic sheeting on ground with wire mesh above. From what I have read, the wire mesh really should have been elevated so that it runs in the middle of the slab, not on the bottom. So the question is, does wire mesh on the bottom do any good at all ? I suspect if this was pointed out to original contractor he would say that if wire was in middle there wouldn't be enough thickness available to lay plumbing without concrete above the pipes being too thin. My answer to that is it never should have been 4 inches in the first place, should have been 6 inches. Thoughts ?
If it is something like 6 x 6 - 10/10ga, the wire adds so little strength to a 4" slab on grade that it barely matters where it is vertically. Ideally, it would be below center, to resist loads from above. But whether a wavey lay, generally 1/2" from the bottom would be any better than one 2" from the bottom (mid point) is about moot. Since small ga wire primarily is used to hold concrete toghether when it does crack, middle would be better for this app.
Far more important would be was the best mix ratio concrete placed with the ideal slump (minimal moisture) and compaction by skilled labor and finished & cured properly for the weather conditions at time of placement. Quite a bit of later concrete cracks are really shrinkage cracks initiated by wet mixes poured fast by unsupervised low bid subs since it "self"-levels and is easy to move around.
"wire" will help keep cracked portions of concrete from shifting & for that purpose should be near the middle of "thin" slabs (under 6") or about 1/3 down from the top in thicker slabs that have significant bar reinforcement in the lower 1/3 of the thickness. IME, it does not practically add much strength in the average installation or keep it from cracking. (unless you are getting down to 4 x 4- 6/6 ga mats) But if you are worried about loads from above, or soil subsidence (as opposed to swelling) then wire or rebar toward the bottom is better.
smt
I have always heard 1/3 in either direction, bottom or top. Middle offers no reinforcement strength at all. Worse, yet, as discussed above, where it ends up during and after the pour is anybody's guess. It floats, it sinks, the workers pull it too high, not high enough, etc... Just not generally worth the effort to even include it. Get your concrete fiber reinforced and let it ride.
I was advised by a wise engineer to not even bother with mesh, but to just go get rebar and cut/tie it myself. After pricing the mesh, I would have needed just over two rolls of mesh, leaving a bunch of leftover. The cost of two rolls was significantly more than the required amount of #3 rebar. You can also custom tailor your rebar to the conditions you will be putting on the floor. I spaced the rebar on 6" centers at the outside edges for the first few courses, then went to 8, 10, 12, 16 and ended up with the very center of the slab at 24" centers. If the edges never crack, the middle won't. I put all the leftover5-6ft pieces in the bay door area spaced between the other pieces, It's about 10" on center from the edge to 10ft inside that door.
If it is something like 6 x 6 - 10/10ga, the wire adds so little strength to a 4" slab on grade that it barely matters where it is vertically. Ideally, it would be below center, to resist loads from above. But whether a wavey lay, generally 1/2" from the bottom would be any better than one 2" from the bottom (mid point) is about moot. Since small ga wire primarily is used to hold concrete toghether when it does crack, middle would be better for this app.
Far more important would be was the best mix ratio concrete placed with the ideal slump (minimal moisture) and compaction by skilled labor and finished & cured properly for the weather conditions at time of placement. Quite a bit of later concrete cracks are really shrinkage cracks initiated by wet mixes poured fast by unsupervised low bid subs since it "self"-levels and is easy to move around.
"wire" will help keep cracked portions of concrete from shifting & for that purpose should be near the middle of "thin" slabs (under 6") or about 1/3 down from the top in thicker slabs that have significant bar reinforcement in the lower 1/3 of the thickness. IME, it does not practically add much strength in the average installation or keep it from cracking. (unless you are getting down to 4 x 4- 6/6 ga mats) But if you are worried about loads from above, or soil subsidence (as opposed to swelling) then wire or rebar toward the bottom is better.
smt
This is your best explanation. Go with it. Mesh is for crack control. If it required structural reinforcement it would be rebar.
I found the plastic chairs/top hat spacers for the mesh were great at setting the height of the mesh, I can really recommend them:
My shed engineer specified the 6" mesh to be one inch from the 4-5" slab surface so I asked around and was told that's pretty normal. There is a constant downward force of many tonnes on the slab (and buried foundations) round the edges from the core filled concrete block walls.
I used plastic chairs to set the mesh height and they worked great, they hold the mesh at the correct height even with the concrete pumping hose resting on it. When we did the pour everyone was walking over the mesh but as their weight came off, the mesh bounced back to correct height. Using the plastic chairs took a lot of guesswork and hassle out of pouring the slab. Looking at the photos, I'd say at worst case the mesh is in the middle. The concrete is PSI as it didn't cost much extra to buy, just less water and more plasticiser additive to the mix.
After three years, there are two cracks width-ways right about where the expansion joins should have gone if the concretor wasn't so lazy to put them in along the 40' long slab.
View attachment View attachment
As others have said.
The mesh itself being seen before the concrete pour on grade is not a concern. This is typical practice for concrete contractors to pour the concrete, and while it is still wet to pull the mesh up as they pour, and as others have stated as the workers then move through the concrete before finishing it they step on it - so there is no firm answer to where it actually ends up (but core samples I have seen show the reinforcing steel usually ends up near the bottom of the concrete when done this way). Reputable contractors will place the reinforcing steel up on plastic or masonry (concrete bricks) spacers before pouring concrete to avoid this.
The reason the reinforcing steel needs to be approximately 1/3 of the concrete depth from the grade is 1) the steel absorbs all the tensile load that is applied to the slab (imagine the slab as a beam, when loaded in the middle it bends downward, putting all the tension in the bottom of the chord) which is in the bottom portion of slab when under load, and 2) the steel needs to be up from the grade far enough that it will not immediately encounter water that is wicked up through the concrete (typical concrete is not waterproof without treatment, but will provide a capillary action for water to climb up through it), hence why most DOT specs call for a minimum concrete cover over any reinforcement steel.
A 4" slab does seem to be lightweight for a commercial property. Realistically for a commercial use slab I would want to see 6-8" concrete thickness with a proper rebar #3-4 (rebar number indicates how many 1/8ths of an inch it is in diamter, so #3 is 3/8ths diameter) used in place of mesh, especially if you will be using the space to store heavy equipment that creates heavy point loads. As others have said the preparation of the subgrade counts heavily in how well your concrete slab may perform.
Really the best way to assuage concerns would be to get a material testing/consulting company to drill cores in the slab of the portion of the property you are looking to purchase. It may take more than one core to hit reinforcing steel, but it will show you what size and where it is - since if there is part of the building that isn't completed it may be that the entire property wasn't all done the same(concrete depth or reinforcing steel). It may also show if there has been settling of the subgrade under the slab, which would be the single biggest reason for any on-grade slab to fail. The testing company will probably also have a PE on staff that will be able to include in their report what the recommended loading for the slab is, although they will of course charge more for his or her time to analyze it.
Geoff
The small wire does add significant strength for crack resistance and to keep cracked portions tight. Even in exterior work, this matters. But the point is that in a 4" slab, for "strength" (resistance to deflecting with external loads) it barely matters where it ends up vertically because if everything else is not right, there is not enough depth of section to resist significant external loads. No matter where you put it in the slab, the geometry is not going to give a high gain in the overall tensile properties of that slab with a load on top. Worse, as has been more or less "argued" in this thread, you don't knwo if the loads on a floor are going to be due to a machine or vehicle "pressing down" in the center (or soil subsidence); or the earth "pressing up" due to perimeter subsidence or, or hydraulic pressure in the center or a combination. I think on a cost/performance basis, wire is better than fiber, which I personally think does not have a good cost/benefit ratio for applications like a shop floor.
As in any other structural application, the individual project needs to be "engineered" for the app and for the budget. In some cases, say a level sidewalk, it might be better to "take" the money for the cost of wire and the cost of placement & control, on merely pouring the sections an additional 1-1/2" thicker, and making good cut joints. In a suspended floor, with "perfectly spec'd and placed concrete" the wire in the moulded sections might allow those sections to safely be 2-1/2" thick and span larger areas, instead of say 4" thick in combination with the way the grid is laid out; saving money on overall concrete volume and weight & accumulated loads elsewhere in the structure. ETC.
I find it astonishing how long metal lasts in concrete even in exterior use after it cracks. But it does begin to set up a vicious cycle of rust and spalling especially if salt is present. Inside without a lot of moisture, it barely degrades.
As others noted, I prefer rebar for adding "strength" to structure, especially in exterior work. If you get into wire in the 6 x 6-6/6 & heavier mats or more closely spaced grid, say 4 x 4, use mats that lay flat & place it carefully and use chairs or masonary support, it can begin to add a lot of strength to the structure. But it still takes some ciphering to decide where to "use" the allocated funds: more reinforcement, or a thicker slab or a "richer" mix to optimize performance per budget? The labor costs can't be ignored in the material calculations, either. Having guys do a perfect job with 4 x 4 - 6/6 wire in a 4,500lb 3-1/2" thick slab may save a lot of concrete cost, but considering the "extra" (labor and steel) is the in-place construction "superior" for the app than a sloppily poured 6" thick 3,000 lb slab with rolled 6 x 6 - 10/10 wire sloppily pulled up from the bottom if it is a garage floor at a similar cost? For a suspended slab with foot traffic, you might want the first. For a garage floor, maybe the latter. If costs are no object, do both (tons of rebar, wire on top for crack control, and a 10" slab)
Many of us in our own garages or add-on shops are reduced to using a 5 bag mix, 4-1/2" or 5" thick, and hope it does not crack too badly. I would work really hard on a compact base, & add wire to the concrete.
Following on my own "economic" ponderings above, I guess what I am saying is that rebar (in the past, it's been a few years for me) seems to add better cost-benefit to a project if it is necessary to add significant "strenght" to a given thickness slab. But wire is useful, and if you can't pour the perfect no-cost-worries slab the thinner wire adds very useful crack control. It won't change whether the slab does or does not crack when the thrash truck accidentally backs over it. Which is closer to the question Milacron seems to be asking.
smt